=='''List'''== | =='''List'''== | ||
| − | * (5hrs) Clean it up! | + | * <s>(5hrs) Clean it up!</s> |
| − | * (4hrs) Finish Glass installation - Glass contractor | + | * <s>(4hrs) Finish Glass installation - Glass contractor</s> |
| − | * (4hrs) Finish Door installation - Glass contractor | + | * <s>(4hrs) Finish Door installation - Glass contractor</s> |
* (1hr) Finish molding work - Glass contractor | * (1hr) Finish molding work - Glass contractor | ||
* (16hrs) Install screen - Need work party | * (16hrs) Install screen - Need work party | ||
| + | * (10hrs) have existing door changed to stay open | ||
* (8hrs) Install Credenza - Work order needed | * (8hrs) Install Credenza - Work order needed | ||
| + | |||
Revision as of 01:54, 12 September 2007
back to OurWork
Project: New Portland Office
Header Info
(38hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
>
List
-
(5hrs) Clean it up! -
(4hrs) Finish Glass installation - Glass contractor -
(4hrs) Finish Door installation - Glass contractor - (1hr) Finish molding work - Glass contractor
- (16hrs) Install screen - Need work party
- (10hrs) have existing door changed to stay open
- (8hrs) Install Credenza - Work order needed
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 38
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: