New Portland Office
back to OurWork
Description
Description: All things necessary to get the new Portland Office operational
Why?
Business Reason: Optimize the workplace
Done When
The office is properly equipped and configured
Useful Links
>
Discussion
Project Lead
- Project Lead: John
Task List
- (2)
Configure Highspeed Internet Routers(John) - (?)
Printer Router Fix(?) -
(16hrs) AboutUs Phone System (John, Isabel) -
(10hrs) AboutUs Data Cable Terminations (John) -
(6hrs) Portland Supplies (John) -
(12hrs) Portland Equipment (John, Vinh) -
(50hrs) Portland Conference Room Completion (John) -
(10hrs) Complete Lease Documentation (John) - (4hrs)
Conference Room Chairs(John) - (10hrs)
Conference Room Doors(John) - (8hrs)
Shades For Office(John)
Resource Estimate
- Hours: Scope of the project not fully defined
Evaluator
- Evaluator: John
Project Evaluation
- How the project went:
- Sign off Person:
- Sign off Date: