Project: New Portland Office
Header Info
(38hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
>
List
- (5hrs) Clean it up!
- (4hrs) Finish Glass installation - Glass contractor
- (4hrs) Finish Door installation - Glass contractor
- (1hr) Finish molding work - Glass contractor
- (16hrs) Install screen - Need work party
- (8hrs) Install Credenza - Work order needed
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 38
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: