Difference between revisions of "Portland Conference Room Completion"
John Stanton (talk | contribs) (New page: <nowiki> <noinclude>{{DistributedPlanningGameNavTo}} Project: New Portland Office =='''Header Info'''== </noinclude>('''38hrs''') [[{{subst:PAGENAME}}]] ('''John''') {{JustTinyEdi...) |
John Stanton (talk | contribs) |
||
| Line 1: | Line 1: | ||
| − | |||
<noinclude>{{DistributedPlanningGameNavTo}} | <noinclude>{{DistributedPlanningGameNavTo}} | ||
Project: [[New Portland Office]] | Project: [[New Portland Office]] | ||
=='''Header Info'''== | =='''Header Info'''== | ||
| − | </noinclude>('''38hrs''') [[ | + | </noinclude>('''38hrs''') [[Portland Conference Room Completion]] ('''[[John]]''') {{JustTinyEditIcon|Portland Conference Room Completion}}<noinclude> |
=='''Description'''== | =='''Description'''== | ||
| Line 48: | Line 47: | ||
__NOTOC__ | __NOTOC__ | ||
</noinclude> | </noinclude> | ||
| − | |||
Revision as of 18:14, 9 September 2007
back to OurWork
Project: New Portland Office
Header Info
(38hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
>
List
- (5hrs) Clean it up!
- (4hrs) Finish Glass installation - Glass contractor
- (4hrs) Finish Door installation - Glass contractor
- (1hr) Finish molding work - Glass contractor
- (16hrs) Install screen - Need work party
- (8hrs) Install Credenza - Work order needed
Task Lead
- Task Lead:
Resource Estimate
- Hours: 38
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: