Difference between revisions of "Portland Conference Room Completion"
John Stanton (talk | contribs) |
John Stanton (talk | contribs) (→'''List''') |
||
| Line 21: | Line 21: | ||
* <s>(4hrs) Finish Glass installation - Glass contractor</s> | * <s>(4hrs) Finish Glass installation - Glass contractor</s> | ||
* <s>(4hrs) Finish Door installation - Glass contractor</s> | * <s>(4hrs) Finish Door installation - Glass contractor</s> | ||
| − | * (2hrs) Clean glass & remove temp safety tape | + | * <s>(2hrs) Clean glass & remove temp safety tape</s> |
| − | * (1hr) Finish molding work - Glass contractor | + | * <s>(1hr) Finish molding work - Glass contractor</s> |
| − | * (16hrs) Install screen - Need work party | + | * <s>(16hrs) Install screen - Need work party</s> |
| − | * (10hrs) have existing door changed to stay open | + | * (10hrs) have existing door changed to stay open - Punch list item |
* (8hrs) Install Credenza - Work order needed | * (8hrs) Install Credenza - Work order needed | ||
Revision as of 20:26, 14 September 2007
back to OurWork
Project: New Portland Office
Header Info
(50hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
>
List
-
(5hrs) Clean it up! -
(4hrs) Finish Glass installation - Glass contractor -
(4hrs) Finish Door installation - Glass contractor -
(2hrs) Clean glass & remove temp safety tape -
(1hr) Finish molding work - Glass contractor -
(16hrs) Install screen - Need work party - (10hrs) have existing door changed to stay open - Punch list item
- (8hrs) Install Credenza - Work order needed
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 50
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: