Line 21: Line 21:
 
* <s>(4hrs) Finish Glass installation - Glass contractor</s>
 
* <s>(4hrs) Finish Glass installation - Glass contractor</s>
 
* <s>(4hrs) Finish Door installation - Glass contractor</s>
 
* <s>(4hrs) Finish Door installation - Glass contractor</s>
* (2hrs) Clean glass & remove temp safety tape
+
* <s>(2hrs) Clean glass & remove temp safety tape</s>
* (1hr) Finish molding work - Glass contractor
+
* <s>(1hr) Finish molding work - Glass contractor</s>
* (16hrs) Install screen - Need work party
+
* <s>(16hrs) Install screen - Need work party</s>
* (10hrs) have existing door changed to stay open
+
* (10hrs) have existing door changed to stay open - Punch list item
 
* (8hrs) Install Credenza - Work order needed
 
* (8hrs) Install Credenza - Work order needed
  

Revision as of 20:26, 14 September 2007

back to OurWork

Project: New Portland Office

Header Info

(50hrs) Portland Conference Room Completion (John)

Description

Description: Complete the conference room construction and installations

Why?

Business Reason: Need conference room to support operation

Done When

All equipment and furniture is installed and operational.

Useful Links

>

List

  • (5hrs) Clean it up!
  • (4hrs) Finish Glass installation - Glass contractor
  • (4hrs) Finish Door installation - Glass contractor
  • (2hrs) Clean glass & remove temp safety tape
  • (1hr) Finish molding work - Glass contractor
  • (16hrs) Install screen - Need work party
  • (10hrs) have existing door changed to stay open - Punch list item
  • (8hrs) Install Credenza - Work order needed

Task Lead

  • Task Lead: John

Resource Estimate

  • Hours: 50

Evaluator

  • Evaluator:

Task Evaluation

  • How the task went:
  • Sign off Person:
  • Sign off Date: