Difference between revisions of "Portland Conference Room Completion"
John Stanton (talk | contribs) |
John Stanton (talk | contribs) |
||
| Line 3: | Line 3: | ||
Project: [[New Portland Office]] | Project: [[New Portland Office]] | ||
=='''Header Info'''== | =='''Header Info'''== | ||
| − | </noinclude>(''' | + | </noinclude>('''50hrs''') [[Portland Conference Room Completion]] ('''[[John]]''') {{JustTinyEditIcon|Portland Conference Room Completion}}<noinclude> |
=='''Description'''== | =='''Description'''== | ||
| Line 21: | Line 21: | ||
* <s>(4hrs) Finish Glass installation - Glass contractor</s> | * <s>(4hrs) Finish Glass installation - Glass contractor</s> | ||
* <s>(4hrs) Finish Door installation - Glass contractor</s> | * <s>(4hrs) Finish Door installation - Glass contractor</s> | ||
| + | * <s>(2hrs) Clean glass & remove temp safety tape</s> | ||
* (1hr) Finish molding work - Glass contractor | * (1hr) Finish molding work - Glass contractor | ||
* (16hrs) Install screen - Need work party | * (16hrs) Install screen - Need work party | ||
* (10hrs) have existing door changed to stay open | * (10hrs) have existing door changed to stay open | ||
* (8hrs) Install Credenza - Work order needed | * (8hrs) Install Credenza - Work order needed | ||
| − | |||
| − | |||
| − | |||
=='''Task Lead'''== | =='''Task Lead'''== | ||
| Line 33: | Line 31: | ||
=='''Resource Estimate'''== | =='''Resource Estimate'''== | ||
| − | * Hours: | + | * Hours: 50 |
<!--* Dollar Cost @ {{PairDayCost}} per pair day:--> | <!--* Dollar Cost @ {{PairDayCost}} per pair day:--> | ||
=='''Evaluator'''== | =='''Evaluator'''== | ||
| Line 42: | Line 40: | ||
* Sign off Person: | * Sign off Person: | ||
* Sign off Date: | * Sign off Date: | ||
| − | |||
| − | |||
[[Category:OperationsTask]] | [[Category:OperationsTask]] | ||
Revision as of 02:01, 12 September 2007
back to OurWork
Project: New Portland Office
Header Info
(50hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
>
List
-
(5hrs) Clean it up! -
(4hrs) Finish Glass installation - Glass contractor -
(4hrs) Finish Door installation - Glass contractor -
(2hrs) Clean glass & remove temp safety tape - (1hr) Finish molding work - Glass contractor
- (16hrs) Install screen - Need work party
- (10hrs) have existing door changed to stay open
- (8hrs) Install Credenza - Work order needed
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 50
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: