Difference between revisions of "Portland Conference Room Completion"
John Stanton (talk | contribs) (→'''List''') |
John Stanton (talk | contribs) |
||
| Line 3: | Line 3: | ||
Project: [[New Portland Office]] | Project: [[New Portland Office]] | ||
=='''Header Info'''== | =='''Header Info'''== | ||
| − | </noinclude>('''50hrs''') [[Portland Conference Room Completion]] ('''[[John]]''') {{JustTinyEditIcon|Portland Conference Room Completion}}<noinclude> | + | </noinclude><s>('''50hrs''') [[Portland Conference Room Completion]] ('''[[John]]''')</s> {{JustTinyEditIcon|Portland Conference Room Completion}}<noinclude> |
=='''Description'''== | =='''Description'''== | ||
Revision as of 19:42, 1 October 2007
back to OurWork , OperationsWork
Project: New Portland Office
Header Info
Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
List
-
(5hrs) Clean it up! -
(4hrs) Finish Glass installation - Glass contractor -
(4hrs) Finish Door installation - Glass contractor -
(2hrs) Clean glass & remove temp safety tape -
(1hr) Finish molding work - Glass contractor -
(16hrs) Install screen - Need work party -
(10hrs) Buy & Install conference room projector brackets (2)Ergo in Demand
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 50
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: