Difference between revisions of "Portland Conference Room Completion"
John Stanton (talk | contribs) |
John Stanton (talk | contribs) |
||
| Line 28: | Line 28: | ||
* (10hrs) have existing door changed to stay open - Punch list item | * (10hrs) have existing door changed to stay open - Punch list item | ||
* (8hrs) Install Credenza - Work order needed | * (8hrs) Install Credenza - Work order needed | ||
| − | * (10hrs) Buy & Install conference room projector brackets (2) - on order Ergo in Demand | + | * (10hrs) Buy & Install conference room projector brackets (2) - on order [http://www.ergoindemand.com/wall-mount-digital-projector.htm Ergo in Demand] |
=='''Task Lead'''== | =='''Task Lead'''== | ||
Revision as of 21:45, 17 September 2007
back to OurWork
Project: New Portland Office
Header Info
(50hrs) Portland Conference Room Completion (John)Description
Description: Complete the conference room construction and installations
Why?
Business Reason: Need conference room to support operation
Done When
All equipment and furniture is installed and operational.
Useful Links
List
-
(5hrs) Clean it up! -
(4hrs) Finish Glass installation - Glass contractor -
(4hrs) Finish Door installation - Glass contractor -
(2hrs) Clean glass & remove temp safety tape -
(1hr) Finish molding work - Glass contractor -
(16hrs) Install screen - Need work party - (10hrs) have existing door changed to stay open - Punch list item
- (8hrs) Install Credenza - Work order needed
- (10hrs) Buy & Install conference room projector brackets (2) - on order Ergo in Demand
Task Lead
- Task Lead: John
Resource Estimate
- Hours: 50
Evaluator
- Evaluator:
Task Evaluation
- How the task went:
- Sign off Person:
- Sign off Date: